The project was initiated in September 2005 with a completion schedule summarized in the table below.

See project deliverables for available work product.



Deliverable/Milestone

Milestone/

Completion Date

Status
Notice to Proceed September 30, 2005 Complete
Complete Field Survey of Existing Drainage Conditions and Develop Baseline Hydrologic Conditions Report

December, 2005

(internal goal)

Complete
Develop and Submit Draft Alternatives Evaluation Report January 25, 2006
Complete
Review Draft Alternatives Evaluation Report February 23, 2006
Complete
Correct/Print Final Alternatives Evaluation Report June, 2006
Complete
Select Preferred Alternative July 31, 2006
Complete
Submit Draft Outfall Systems Preliminary Design Report January 2, 2007
Complete
Review Draft Outfall Systems Preliminary Design Report February, 2007 Complete
Correct and Print Final Outfall Systems Plan Preliminary Design Report March, 2007
Complete