Deliverable/Milestone |
Milestone/
Completion Date
|
Status |
| Notice to Proceed |
September 30, 2005 |
Complete |
| Complete Field Survey of Existing Drainage Conditions and Develop Baseline Hydrologic Conditions Report |
December, 2005
(internal goal) |
Complete |
| Develop and Submit Draft Alternatives Evaluation Report |
January 25, 2006 |
Complete |
| Review Draft Alternatives Evaluation Report |
February 23, 2006 |
Complete |
| Correct/Print Final Alternatives Evaluation Report |
June, 2006 |
Complete |
| Select Preferred Alternative |
July 31, 2006 |
Complete |
| Submit Draft Outfall Systems Preliminary Design Report |
January 2, 2007 |
Complete |
| Review Draft Outfall Systems Preliminary Design Report |
February, 2007 |
Complete |
| Correct and Print Final Outfall Systems Plan Preliminary Design Report |
March, 2007 |
Complete |
|
 |
 |