The project was initiated in April 2009 with a completion schedule summarized in the table below.

See project deliverables for available work product.

Deliverable/Milestone

Milestone/

Completion Date

Status
Notice to Proceed   April 2009
Phase A--Development of Alternatives
Baseline Hydrology (Draft) 01/27/2010
Completed
Baseline Hydrology (Final) 04/16/2010
Completed
Development of Alternatives (Draft) 09/24/2010
In Progress
Cost/Benefit Analysis (Draft) 09/24/2010
Alternative Report (Final) 11/30/2010
Select Alternative 01/28/2011  

Phase B Conceptual Design
Conceptual Design Report (Draft) 03/31/2011  
Conceptual Design Report (Final) 05/27/2011
FHAD    
FHAD (Draft) 08/20/2010
In Progress
FHAD (Final) 10/22/2010
FIRM Information Development TBD